Caetano,
Thanks for your reply ,yes checked if there are any inconsistency earlier
Did run consistency program ,how ever it didn't clear the NPROC
As said ,before MRP run, we had planning horizon as 99 days ,which we increased to 500 days for testing ,when i ran MRP it did generate planned order for NPROC and also it generated dependent requirement ,which created this duplicate scenario.
Please confirm ,how to handle this NPROC in general.as for now sales order is delivered ,NPROC is stuck in MD04 and with out undergoing any changes with existing planning horizon ,as these are backdated in Jan or Feb 2015
One more question :
Also,upon planned order generation for any sales order requirement ,this REM planned order if not converted as production order and backflush for the parent assembly happens , would that delete the planned order generated and create NPROC for post processing ?
thanks,Srini