Hello Gurus,
We have a scenario where we are shipping only on Monday Tuesday to DC 'x' and Wednesday Thursday to DC 'y' . We tried shipping calendar but that is location specific and we can assign only one shipping calendar to the source location . I tried transportation calendar but if we have Monday Tuesday for tlane between plant and DC 'x' with a transportation duration of 4 days then the goods are reaching the DC after 2 weeks as it is taking Monday Tuesday of current + Monday Tuesday of next week = 4 days .
I want it to start on Monday and be available on Friday . Is this achievable
Regards,
Nick