Let me explain you with an example, let's assume you have 10 production lines and each line needs an operator to run these machines. But we have only 8 operators (this being pooled capacity) which can run these lines. So finally it would be 8 lines which would be running as we have capacity constraint of the pooled capacity.
I hope this explains you the concept.