Hello Deepak,
For every scheduling run, the system creates a scheduling log in the production order. The log records all information that is important for scheduling.
Please check the scheduling log Goto -->Logs--> Scheduling.
Also note system will do the forward scheduling if order goes back today date.
Best Regards,
R.Brahmankar