Dear Experts ,
I have an issue with incorrect planned deliver date for raw materials.
I have a raw materials-X, for which planned delivery time is maintained as 3 days in material master,
After MRP Run(today) , system has generated a purchase requisition in which planned delivery date is displayed as 06.12.2014.
Holidays set in factory calender (2-days Friday and Saturday) . How system has proposed this date 06.12.2014, why the planned deliver time is
considered more than 3 days..?
Regards,