Hi,
Imran Mohammed wrote:
as mentioned and as we are all aware, the std jobs imports to QA system all the TR irrespective of TR type. However, is this possible that i schedule this job in background with some link to project phase. Lets say, when the phase of project is "In Dev. With release" this job should import ToC and when phase is "Test" this should import original TR.
its the default functionality in Charm.
If you are in In Dev with release - Only TOC relased and when you set the status "Successful Test" in Change document then your orginal TR get relased.
Import_All job import the request already in q, and urgent changes and TOC. once TOC get confirmed after that your orginal TR released and imported to QA and moved to PRD buffer.
Please check,
https://websmp108.sap-ag.de/~sapidb/011000358700000478072011E/index.htm
Thanks
Jansi