Quantcast
Channel: SCN: Message List
Viewing all articles
Browse latest Browse all 8635

Re: MTO scenario with sales order

$
0
0

So in this case if I want to do a valuated sales order stock to post the actual costs on a PP order to reflect in COGS at PGI at what price does the sales order cost estimate does the costing?

 

It does based on the price control 'S' or 'V'.

 

But if i have a PP order which has planned costs based on the PO price of the materials procured then can this Sales Order Cost Estimate valuate the product based on that?

 

If yes, then should my sequence be like:

 

1) Create Sales Order

2) Planned Order

4) Run MRP

5) Create PR and POs.

6) Convert Plnd order to Prod Order.

7) Can Planned Cost Variant on the PP order pull the PO price of the RM and calculate the planned costs?

8) If yes, then after step 6 do I have to run the Sales ORder Cost Estimate (Product Costing) to valuate the planned Sales Order stock?

 

Please confirm?

 

Appreciate your help.

Raj


Viewing all articles
Browse latest Browse all 8635

Trending Articles



<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>